News | Jun 30, 2026

GS1-3 Hotfire Updates

June 30, 2026

We're not rebuilding the same pad for New Glenn. We're moving to a horizontal/vertical hybrid configuration to get us flying again this year at 36A. We were already working on something similar for 9x4 at 36B. Let me explain what that means. We mate the stages horizontally in the Integration Facility (IF). Then we bring the integrated vehicle out to the pad, use a crane to perform the vertical breakover, and mate the payload once New Glenn is vertical. This new ConOps has the added benefit of increasing our flight cadence as well.

Read more about the path forward here.

CEO Dave Limp, X

June 1, 2026

Some LC-36 updates. Now that we’ve had access to the pad and integration facility we can share a bit of good news. The propellant farm, oxygen, liquid hydrogen and LNG tanks are all in good shape. This is good luck because these are very long lead items. The water tower is also good. The big support tower is damaged, but it can be repaired in place rather than torn down and replaced. The booster “Never Tell Me The Odds” and the three GS-2s that were onsite in the integration facility also look good.

I’ve seen some speculation that we might move directly to the 9x4 configuration, but we won’t do that. Rate manufacturing of 7x2 is going well, and we’re going to continue that at pace as planned and store the stages for use. In addition, we had already been working for some time on eliminating our transporter-erector in favor of an alternative vertical conop, and we’ll now go directly to that; so we don’t need a new transporter-erector.

We will fly again before the end of this year. Gradatim Ferociter.

CEO Dave Limp, X

May 30, 2026

We have regained some access to Launch Complex 36 and are actively investigating the hotfire anomaly. We will start clearing the pad soon and have a good rebuild plan in place. The booster and GS2s in the integration facility appear healthy from quick looks.

CEO Dave Limp, X

May 29, 2026

Debris from our recent hotfire anomaly may wash ashore in the coming days/weeks. If you encounter any debris, do not touch or approach it for your safety.

Please report the location immediately:
Call: 1-321-222-4355 
Email: MissionRecovery@blueorigin.com

Blue Origin, X 

May 28, 2026

We experienced an anomaly during today's hotfire test. All personnel have been accounted for. We will provide updates as we learn more.

Blue Origin, X 

Latest Posts

  • Jun 30, 2026
    News

    New Glenn Return to Flight

    A note from CEO Dave Limp: On May 28, 2026, we experienced a significant anomaly during a New Glenn Integrated Launch Vehicle hotfire test. I want to provide you with an update on the remarkable recovery and rebuild efforts since that day, and our path forward to return to flight this year. 

  • Jun 30, 2026
    A starry sky.
    News

    GS1-3 Hotfire Updates

    We experienced an anomaly during a hotfire test on May 28, 2026. All personnel have been accounted for. We will provide updates as we learn more.

  • Apr 16, 2026
    News

    New Glenn’s Third Mission Slated for April 19

    Blue Origin announced the launch date for New Glenn's third mission, slated to launch no earlier than Sunday, April 19, 2026.